Summary of Baseline Results – Delays Associated with Bribes . | ||
---|---|---|
Service Type . | Estimated Delay Associated with Bribe Requests . | Specification . |
. | Penalty factor: ratio of the wait time faced by firms confronted with bribe demands to that of those that were not . | . |
A Construction permit | 1.77 | (Table 3, Column 1) |
1.73 | (Table 3, Column 2) | |
1.53 | (Table 3, Column 3) | |
1.46 | (Table 3, Column 4) | |
An operating license | 1.56 | (Table 4, Column 1) |
An electrical connection | 1.45 | (Table 4, Column 2) |
Customs clearance to export | 1.15 | (Table 4, Column 3) |
Customs clearance to import | 1.36 | (Table 4, Column 4) |
Summary of Baseline Results – Delays Associated with Bribes . | ||
---|---|---|
Service Type . | Estimated Delay Associated with Bribe Requests . | Specification . |
. | Penalty factor: ratio of the wait time faced by firms confronted with bribe demands to that of those that were not . | . |
A Construction permit | 1.77 | (Table 3, Column 1) |
1.73 | (Table 3, Column 2) | |
1.53 | (Table 3, Column 3) | |
1.46 | (Table 3, Column 4) | |
An operating license | 1.56 | (Table 4, Column 1) |
An electrical connection | 1.45 | (Table 4, Column 2) |
Customs clearance to export | 1.15 | (Table 4, Column 3) |
Customs clearance to import | 1.36 | (Table 4, Column 4) |
Source: Authors' analysis based on data from Enterprise Surveys, various years.
Summary of Baseline Results – Delays Associated with Bribes . | ||
---|---|---|
Service Type . | Estimated Delay Associated with Bribe Requests . | Specification . |
. | Penalty factor: ratio of the wait time faced by firms confronted with bribe demands to that of those that were not . | . |
A Construction permit | 1.77 | (Table 3, Column 1) |
1.73 | (Table 3, Column 2) | |
1.53 | (Table 3, Column 3) | |
1.46 | (Table 3, Column 4) | |
An operating license | 1.56 | (Table 4, Column 1) |
An electrical connection | 1.45 | (Table 4, Column 2) |
Customs clearance to export | 1.15 | (Table 4, Column 3) |
Customs clearance to import | 1.36 | (Table 4, Column 4) |
Summary of Baseline Results – Delays Associated with Bribes . | ||
---|---|---|
Service Type . | Estimated Delay Associated with Bribe Requests . | Specification . |
. | Penalty factor: ratio of the wait time faced by firms confronted with bribe demands to that of those that were not . | . |
A Construction permit | 1.77 | (Table 3, Column 1) |
1.73 | (Table 3, Column 2) | |
1.53 | (Table 3, Column 3) | |
1.46 | (Table 3, Column 4) | |
An operating license | 1.56 | (Table 4, Column 1) |
An electrical connection | 1.45 | (Table 4, Column 2) |
Customs clearance to export | 1.15 | (Table 4, Column 3) |
Customs clearance to import | 1.36 | (Table 4, Column 4) |
Source: Authors' analysis based on data from Enterprise Surveys, various years.